 7th to 13th November 2005

Plaster still going up - only 2 days this week - more next week.

Next main job painting - sealing the plaster with a weak wash and then top coats.  When the top coats are on then the downlighters have started to be installed.  We're going to use 9w compact fluorescent bulbs in downlighters - they do have a slight warm up period but look fine otherwise and use much less energy than 50w and pump out far less heat.

Can't think of much more to say for this week - just a steady week of progress.  Oh and thanks to my son I'll make a first appearance in one of the photos this week!!