 19th to 25th September 2005

The plasterers were finishing another job this week so I finished off the preparation for the ground floor and then moved down into the basement to build up the false walls on the external walls.  These are then packed with rockwall and sheathed with plasterboard.

Whilst I was hiding in the basement Jason was finishing off trenches for the water pipes to the road and the last drain trench.

We also started on the drainage from the septic tank.

A fairly quiet week but back into full strength next week.