17 to 23 Oct
Build Home Land Search The Site Planning Design Build Diary Links/Suppliers Contact Us

Click on the images below to see a larger version.

 17th to 23rd October 2005

Steve and Rich the plasterers were delayed on another job this week so we plugged away at more prep work - insulating and plasterboarding the rear draught lobby, building false walls in the basement and plasterboarding the ceilings and walls.

Doesn't sound a lot when put like that but it was and it filled the week up easily!!