 9th to 15th May 2005

Payback time for last weeks underordering!

Some of the top coat went on and looks great - well it looked awful to start with but when it was scraped back ( as K-Rend should be) it then looked great.  But then we stopped - all for the want of 4 bags of base coat but could SAS get it to us - oh no we don't actually keep stocks of basecoat in the country it is all shipped in from Ireland to order.  Thinks there is a damn good reason not to have used K-Rend.......

Anyway we did loads of other stuff - a down pipe where the render was finished, loads of grunt work on the sprinkler system - making sure we had sufficient drop to fit the sprinkler heads in, lighting cables, power cables, back boxes, cable protectors, false ceilings and topped off with the first bit of UFH pipe going into a ceiling void.

It is all coming along quite nicely but the underordering still bugs me......silly me.