Click on the images below to see a larger version.29th August to 4th September 2005
Another short week with the Bank Holiday but we managed to get the top
floor totally ready for plastering.
This meant finishing off the window reveals with plasterboard, fitting door linings and fitting plasterboard into the steel beams over the windows. Also we got some scaff
erected so we can deal with the high ceilings in the hall. The floor was covered with hardboard to prevent damage to the screed and make clearing up easier after plastering.
As well as this we started on the back wall
of the kitchen. This is partly below ground so has a false wall that is insulated and then covered with a vapour barrier and then plasterboard.
A bit in advance but I also bought the stone flags for the ground
floor - having found a price worth jumping at!
Monday plastering.......