Click on the images below to see a larger version. 15th to 22nd August 2004 Despite the rain the 1st floor walls went from zero to complete this week - nice when something
goes right! This week was mainly spent making sure I have all of the timber for wall plate, roof , attic floor and the insulation boxes on the outside of the house sorted for next week so we can crack on
with that. Other than that a very gentle week hoisting blocks and muck up the scaffold so the whirlwinds in the blocking gang can keep going - 11 packs of blocks on the first day alone! I have
also arranged for the scaffolding to be raised one lift - let's hope that is less tramatic than the first lift.
I picked up a couple of oak lintles from Dean Oak - they are going to look great built into the stone. |