 28th March to 3rd April 2005

This week was spent dodging the rain - whilst wet plumbing and when dry block laying around the rear lobby.

The plumbing came along well including pressure testing all of the runs completed todate.  This meant we could get on and insulate the pipe runs as surprisingly all of the joints were sound!

The block laying was reasonable but I'm not sure of the strength of a pier at one end of the run which is going to support a 4m glulam beam - but we'll see!

Other than that fairly uneventful - more slog with not much of interest to show!  Oh yes decided to catch some of the mice in the house (humanely of course) - 4 so far.