21st to 27th February 2005

The last major window went in on Monday - rather large and in 3 peices but by lunchtime all was done - thank goodness.

The rest of the week was spent on clearing the ground floor, running the soil pipes, planning routes for waste, hot and cold water and vents for the MVHR system.

All components for the vents were ordered -from Rega ( a nice DC powered system) and from Fans Direct (cheaper on standard vent pipes).

All the copper was ordered for the plumbing.

We also decided on how the external panels will be finished - we'll use a stainless lath coated with render - now to line someone up to do it!