Click on the images below to see a larger version. 14th to 27th March 2005
Two weeks - the first week was a week off so no action.
The next week was slow as we're still shorthanded due to holidays and things.
We started on blocklaying around the rear draught lobby or porch - I was merrily getting rendering sorted until I realised that this would
need to be completed first. This also needed a large glulam beam to act as a wall plate above the 2 windows and doorway that will make up this wall.
When we were getting this delivered we also got a stack of 4x2
and 3x2 to use to construct the false ceilings underneath the beam and block floors.
Yet more deliveries - all of the ventiliation kit from Rega.
Otherwork - plumbing and starting to run vent pipes. Will soon
be time to pressure test the pipework - I wonder how good my joints really are???