 14th to 27th March 2005

Two weeks - the first week was a week off so no action.

The next week was slow as we're still shorthanded due to holidays and things.

We started on blocklaying around the rear draught lobby or porch - I was merrily getting rendering sorted until I realised that this would need to be completed first.  This also needed a large glulam beam to act as a wall plate above the 2 windows and doorway that will make up this wall.

When we were getting this delivered we also got a stack of 4x2 and 3x2 to use to construct the false ceilings underneath the beam and block floors.

Yet more deliveries - all of the ventiliation kit from Rega.

Otherwork - plumbing and starting to run vent pipes.  Will soon be time to pressure test the pipework - I wonder how good my joints really are???