Click on the images below to see a larger version.14th to 20th February 2005
Monday saw the last 2 Oak beams arrive and work start on the two large windows
remaining. On Wednesday with extra help on site we fitted the upper window with surprising ease. The lower one, being in 3 parts, should have also gone in this week but one labourer had bad trouble so it was
delayed until next week.
The loft fitting continued, the end of the week seeing 95% being completed.
Work also started on running the soil pipes in place. Very wierd to have spent a year going up and now
starting to come back down through the house again!